PROJECT EXPERIENCES

PROJECT EXPERIENCES

SUBSTATION

No.Project TitleClient
1Establishment of 132/33kV PMU Enstek and Construction of Access Road Tenaga Nasional
Berhad
2Supply, Erect and commissioning of 132/33kV Switchgear, 2 x 45MVA Power Transformers, Ancillary Equipment complete with Associated Civil Works for the extension of 2 Transformer Bays at Pontian 132/33/11kVTenaga Nasional
Berhad
3Supply, Erect and Commissioning of 275kV, 132kV Switchgear, 240MVA 275/132kV Transformers, ancillary equipment & associated civil works for Rantau SubstationTenaga Nasional
Berhad
4Supply, Erect and Commissioning of 275/132kV Switchgear, Ancillary Equipment and Associated Civil Works for 275/132kV Gelang Patah Substation Tenaga Nasional Berhad/ AMBC Controls
5Supply and Erection 132/11kV Swichgears, Transformers, Ancillaries Equipment and Civil works for Menglembu, Green Town, Kg. Binjai, Batu Uban, Bayan Lepas (Extn) and Farlim (Extn) GIS Substations
(Penang state)
Tenaga Nasional
Berhad
6Supply and Erection 132kV GIS Switchgear, 33kV Switchgears and ancillary equipment for Johor Baharu City Center (JBCC) Substation.Tenaga Nasional
Berhad
7Supply, Delivery, Installation and Commissioning of 21 Nos. 33/11kV SubstationTenaga Nasional
Berhad
8Supply, Erection, and commissioning of 132kV Switchgears, Ancillaries, Transformers and Civil Works (Kg. Subang, Parit Buntar, Teluk Intan and Pasak Substations)Tenaga Nasional
Berhad
9Establishment of 2nd Transformers (1x90MVA) at PMU 132/33/11kV Mergong, KedahTenaga Nasional
Berhad
10Supply and install one (1) unit 275/132kV 240MVA YNa0d1 Auto Transformer to TNB Assets Maintenance Department for use as strategic spareTenaga Nasional
Berhad
11Supply and Install of 1 unit 3 phase 132/33kV 90MVA YNd1 at PMU Taman Jaya Tenaga Nasional
Berhad
12Supply, install and commissioning of 1 unit 275/132kV 240MVA YNA0D1 autotransformer at PMU Skudai Tenaga Nasional
Berhad
13Supply, install and commissioning of 1 unit 275/132kV 240MVA YNA0D1 autotransformer at PMU Bukit Merah Tenaga Nasional
Berhad
14Supply, Erect and Commissioning of 132kV Switchgear & Ancillary equipment & associated civil works for Banting SubstationTenaga Nasional
Berhad
15Design & Build Substation building, installation, testing & commissioning of 33/ 11kV 2 x 7.5MVA transformer, 33kV Switchgear and ancillary equipment for Summerset, RompinTenaga Naional Berhad/
Kejuruteraan Yakinniaga

PROJECT EXPERIENCES

TRANSMISSION

No.Project TitleClient
1Sabah East-West Grid Interconnection Overhead Transmission Line TTSB-SPK
CONSORTIUM
2Proposed LILO Existing 132kV Underground Cable between PMU Bukit Tengah - Gelugor-Bayan Baru to PMU Bayan MutiaraTenaga Nasional
Berhad
3Proposed 275kV Double Circuit looping in/out from existing 275kV Segari - Ayer Tawar to Vale Iron Ore Plant (Mainhead B) Tenaga Nasional
Berhad
4Implementation of 275/132KV Transmission Line project in Transmission Development 1997 - Stage 3 (Mainhead A)Tenaga Nasional
Berhad /
Kejuruteraan
Yakiniaga
5Proposed 275kV Bulk supply to Bahru Stainless (275kV Double Circuit Overhead line from PMU Cahaya Baru to Bahru Stainless Substation)Tenaga Nasional
Berhad
6Proposed Transmission Line Reconductoring of 132kV Hicom-Proton using High capacity conductor, 132kV LILO into PMU Teluk Panglima Garang & T-OFF into PMU Pandamaran and 132kV LILO into PMU Taman JayaTenaga Nasional
Berhad
73 x 700MW Coal Fired Power Plant, Tanjung Bin, Johor Tenaga Nasional Berhad/ Tg. Bin Power
8100 MW Gas-Fired Power Generation Project for Sabah Electricity Sdn Bhd (Kayumadang 132kV Substation)ABB Malaysia Sdn Bhd
9Implementation of 275/132KV Transmission Line project in Transmission Development 1997 - Stage 2 (Mainhead A)Tenaga Nasional Berhad / Kejuruteraan Yakiniaga
10Cadangan Merekabentuk, Membina, Melengkap, Menyiapkan, Mentauliah dan Menyelenggarakan kerja-kerja satelit untuk Tambahan Kampus University Teknologi Mara di Lot PT 1567 & 1568, Mukim Jeram, Daerah Kuala Selangor, Selangor Darul EhsanU-WOOD
11Supply, Erection & Commissioning of Transmission Line for KTMB crossing at 132kV Bukit Batu - Seelong and 132kV Tebrau- Kangkar Tebrau Tenaga Nasional Berhad
12Electrified Double Track Project - Rawang to Ipoh. Relocation of TNB Overhead Transmission and Distribution Line (22kV to 275kV)COMTRACT Sdn Bhd

PROJECT EXPERIENCES

DUBAI, UAE

No.Project TitleClient
1Supply, Installation, Testing & Commissioning of Trade Centre Round-About & Mall 132/11kV Substation and Associate WorksDubai Electricity &
Water Authority
(DEWA)
2Supply, Installation, Testing & Commissioning of industrial City 1 & Industrial City 2 132/11kV Substation and Associated WorksDubai Electricity &
Water Authority
(DEWA)

PROJECT EXPERIENCES

CURRENT PROJECT HANDLING

No.Project TitleClient
1UNDERGROUND CABLE 132KV RETICULATION TO PMU PASIR GUDANG POWER STATION NORTH (PGPN) Tenaga Nasional Berhad
2PERLAKSANAAN PROJEK MEMPERKUKUHKAN SISTEM 33KV DI PMU NEW SERDANG KE PPU EQUINE PARKTenaga Nasional Berhad/ Tenaga Cable Industries Sdn Bhd (TCI)